From FY 2024‑25, the CEA’s Legal Division director will annually verify cross‑state CGP status under Rule 3 of the Electricity Rules, 2005. Applicants must file by May 31 with proof of 26% equity ownership and 51% energy consumption. Separate metering, SPV disclosures and ESS roles apply, and a two‑tier appeal is available.
Interstate Captive power plants finally get verification framework
From FY 2024‑25, the CEA’s Legal Division director will annually verify cross‑state CGP status under Rule 3 of the Electricity Rules, 2005. Applicants must file by May 31 with proof of 26% equity ownership and 51% energy consumption. Separate metering, SPV disclosures and ESS roles apply, and a two‑tier appeal is available.