Rajasthan’s new SOP under the Rajasthan Integrated Clean Energy Policy, 2024 streamlines renewable energy projects by standardising registration, evacuation approvals, and commissioning. Developers must meet net worth criteria, submit technical plans, and secure approvals from DISCOMs or RVPN. Projects above 5 MW must integrate battery storage. The SOP also mandates annual captive compliance, requiring 51% consumption and 26% equity, failing which projects are treated as third-party sales with additional charges.
Rajasthan SOP Boosts Captive and Third‑Party Renewable Projects
Rajasthan’s new SOP under the Rajasthan Integrated Clean Energy Policy, 2024 streamlines renewable energy projects by standardising registration, evacuation approvals, and commissioning. Developers must meet net worth criteria, submit technical plans, and secure approvals from DISCOMs or RVPN. Projects above 5 MW must integrate battery storage. The SOP also mandates annual captive compliance, requiring 51% […]